[OPEN-ILS-DEV] Evergreen 2.11 proposed release schedule
Mike Rylander
mrylander at gmail.com
Wed Sep 7 15:29:35 EDT 2016
Heads up, all!
If you're a committer and were planning to merge any pre-RC bug fix
branches, now's the time to do so. If we can avoid DB updates, that'd
be best, but I'll leave that up to committers doing the committing.
For my part, I'll be committing two branches today in prep for the RC release.
Thanks, and happy merging!
--
Mike Rylander
| President
| Equinox Software, Inc. / Open Your Library
| phone: 1-877-OPEN-ILS (673-6457)
| email: miker at esilibrary.com
| web: http://www.esilibrary.com
On Wed, Aug 10, 2016 at 3:44 PM, Mike Rylander <mrylander at gmail.com> wrote:
> UPDATE!!!
>
> By consensus during today's dev meeting in IRC, we're pushing back the
> Beta release date by one week. The new date is August 24.
>
> This does not effect the RC or final release dates, which remain as
> listed below.
>
> Thanks, all!
>
> --
> Mike Rylander
> | President
> | Equinox Software, Inc. / Open Your Library
> | phone: 1-877-OPEN-ILS (673-6457)
> | email: miker at esilibrary.com
> | web: http://www.esilibrary.com
>
>
> On Fri, Jun 3, 2016 at 3:18 PM, Mike Rylander <mrylander at gmail.com> wrote:
>> Hello all!
>>
>> Only a day late than originally promised, here is the proposed
>> schedule for the 2.11 release.
>>
>> 2.11 Alpha: Wednesday, July 27
>> 2.11 Beta and feature freeze: Wednesday, August 17, three weeks later
>> 2.11 RC1: Wednesday, September 7, three weeks later
>> 2.11.0: Wednesday, September 21, two weeks later
>>
>> As mentioned, it hews closely to the 2.9 schedule, just shifting a
>> week here or there. Like Jason did, I want to align the beta feature
>> freeze and .0 cutting with regular maintenance releases of prior
>> versions.
>>
>> I promised a set of lists along with the schedule setting down the LP
>> bugs I hope to help wrangle before the Beta cut-off. Unfortunately
>> for the purpose of making the promised email deadline (and fortunately
>> for every other purpose) bug squashing day kept changing those lists
>> right under me! Thus, my delay in this email. I'll be revising that
>> separately and sending that along soon.
>>
>> Thanks, all! Questions? Ask away.
>>
>> --
>> Mike Rylander
>> | President
>> | Equinox Software, Inc. / Open Your Library
>> | phone: 1-877-OPEN-ILS (673-6457)
>> | email: miker at esilibrary.com
>> | web: http://www.esilibrary.com
More information about the Open-ils-dev
mailing list