George,
I'm not sure I understand what you are saying. The workflow diagram says
that if you are not ordering through EDI, print the order. If I understand
you correctly, you may have a situation where you orderd on Amazon but you
will also be maintaining a separate record in Evergreen Acquisitions and
simply never print a purchase order because Amazon would not accept it.
Is that correct?
Tim
On Tue, May 1, 2012 at 10:20 AM, Duimovich, George <
George.Duimovich at nrcan-rncan.gc.ca> wrote:
>
> One thing we'd like to see improved with the current workflow
> http://goo.gl/5AhcP is an option for more streamlined electronic orders
> (e.g. When "Provider accepts electronic orders" = yes).
>
> The basic use case is where electronic orders are accepted but not via EDI
> -- instead, just classic credit card order via direct web through sites
> like Amazon and so on. This is partly a documentation issue (not clear what
> to do as you walk through this use case for the first time since "Yes"
> above points to EDI only in the workflow diagram) but there probably could
> be some UI improvements to streamline cases where you are working via
> online web orders and get immediate feedback about order and shipping
> status and don't need to print or send out a purchase order, etc.
>
> George
>
> George Duimovich
> NRCan Library / Bibliothèque de RNCan
>
>
>
> -----Original Message-----
> From: open-ils-general-bounces at list.georgialibraries.org [mailto:
> open-ils-general-bounces at list.georgialibraries.org] On Behalf Of Kathy
> Lussier
> Sent: April 30, 2012 17:13
> To: open-ils-general at list.georgialibraries.org
> Subject: [OPEN-ILS-GENERAL] Acquisitions issues
>
> Hi all,
>
> I'm taking this opportunity to be loud on a couple of acquisitions
> problems we've encountered.
>
> We have two consortia that are going live on Evergreen in less than a
> month. This morning, I sat down with the acq people at one consortium to
> identify the issues that will be most problematic for them when they go
> live. I'm hoping we can work to get these issues resolved so that the
> transition to acquisitions in Evergreen can go as smoothly as possible.
>
> * https://bugs.launchpad.net/evergreen/+bug/969494 describes a problem
> where using the "Add to Purchase Order" option from the View/Place Orders
> interface does not carry over the PO's provider to that lineitem.
> Consequently, the PO cannot be activated. We have several libraries who do
> not plan to use selection lists, and fixing this problem will make a big
> difference in their workflow.
>
> * I also added a new bug today for problems we encountered when trying to
> activate a PO as part of the order record upload process.
> https://bugs.launchpad.net/evergreen/+bug/992108. Since the workaround
> for this isn't too onerous (uploading directly to the PO and then
> activating), it probably isn't as high of a priority as my first item, but
> it is still fairly important.
>
> * We also are having ongoing problems with EDI order responses. From the
> acquisitions discussion Saturday morning, it sounds like nobody is working
> with order responses. We are committed to putting in some of the legwork to
> try to figure out what the problems are and to get order responses working
> properly so that acquisitions can become a more attractive option for other
> Evergreen users.
>
> However, we have encountered some problems that I suspect might not be
> bugs, but may be related to configuration issues, and we just need to know
> where to start looking to resolve these problems. I sent something to the
> list regarding this issue earlier this month,
> http://markmail.org/message/gjn4eiadi7s55jdt, but I'll try to provide
> more detail below.
>
> We have been working with a vendor that has been posting test order
> responses. We have been able to successfully translate these order
> responses two times, and both times occurred on the day after we performed
> an Evergreen update on our test system.
>
> Afterwards, we get an error in our EDI messages every day. It seems as if
> the system keeps trying to translate that same message that had already
> been successfully translated after our Evergreen update.
>
> The status of these messages is trans_error.
>
> The error message is:
> EDI Translator edi2json failed, Error 2: Uncaught exception Input/output
> error in method edi2json
>
> The EDI Message Body is:
>
> UNB+UNOA:3+1697978:31B+3075052:31B+120328:1751+00000000000011++EANCOM'UNG+ORDRSP+1697978:31B+3075052:31B+120328:1751+00000000000007+UN+D:96A'UNH+00000000000007+ORDRSP:D:96A:UN:EAN008'BGM+231+148+29'DTM+137:20120313:102'RFF+ON:148'NAD+BY+20N6885::91'NAD+SU+1697978::31B'LIN+166+5+9780060186944:EN'PIA+5+0060186941:IB'QTY+21:1'PRI+AAF:22:CA:SRP'RFF+LI:148/166'LIN+167+5+9780142437261:EN'PIA+5+0142437263:IB'QTY+21:1'PRI+AAF:7:CA:SRP'RFF+LI:148/167'LIN+168+5+9780152052201:EN'PIA+5+0152052208:IB'QTY+21:3'PRI+AAF:6.95:CA:SRP'RFF+LI:148/168'LIN+169+2+:EN'PIA+5+:IB'QTY+21:1'QTY+12:0'FTX+LIN++200:1B:28'PRI+AAF:5:CA:SRP'RFF+LI:148/169'LIN+170+5+9780345475800:EN'PIA+5+0345475801:IB'QTY+21:1'PRI+AAF:14.95:CA:SRP'RFF+LI:148/170'UNS+S'CNT+2:5'UNT+36+00000000000007'UNE+1+00000000000007'UNZ+1+00000000000011'
>
>
> Any thoughts on where we can start troubleshooting this?
>
> Thanks!
> Kathy
>
> --
> Kathy Lussier
> Project Coordinator
> Massachusetts Library Network Cooperative
> (508) 756-0172
> (508) 755-3721 (fax)
> klussier at masslnc.org
> Twitter: http://www.twitter.com/kmlussier
>
--
Tim Spindler
tjspindler at gmail.com
*P** Go Green - **Save a tree! Please don't print this e-mail unless it's
really necessary.*
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://libmail.georgialibraries.org/pipermail/open-ils-general/attachments/20120501/f89b9529/attachment-0001.htm>
More information about the Open-ils-general
mailing list