[OPEN-ILS-DEV] EG 2.3.beta2 this Friday
Bill Erickson
erickson at esilibrary.com
Mon Aug 13 09:35:38 EDT 2012
Hi All,
I'm planning on cutting 2.3.beta2 this Friday 8/17. Keep the bug fixes rolling!
After that comes the 2.3.rc1 release candidate on August 31st. I'm not anticipating an RC2, but we can certainly squeeze one in if necessary.
<policy>
How do we characterize bug fixes that are allowed to be merged between RC1 and GA? I assume we should limit to showstoppers only?
</policy>
The General Availability release is scheduled for Sept. 19th.
By the way, who owns the "Evergreen ILS Developers" Google Calendar and would that someone mind adding these dates to the calendar (or giving me write access)?
Thanks
-b
--