> As we look toward planning the next release of Evergreen (after 2.2), there are a couple of simple, but important questions we need to answer.
>
> 1. Is it time to jump to 3.0 or do we stay with 2.3?
>
> I'm not aware of any significant architectural changes (e.g. changing PG versions) on the horizon, which would suggest we stick with 2.3.  Perhaps it's too early to tell?
>
> For reference: http://evergreen-ils.org/dokuwiki/doku.php?id=versioning

I vote for 2.3, with a corollary of changing "major feature release"
criteria to "minor feature release would be 2 digits otherwise".
Infrastructure is pretty much always changing.

For example, the next releases would be:

2.3
2.4
...
2.9
3.0 (to avoid 2.10)

> 2. Do we return to the originally proposed March/September release schedule?
>
> My impression is there's a general consensus to do this.  It would lead to a shortened development cycle for next release, so I would like to give everyone a chance to voice their concerns / alternate suggestions and put this to a vote.

+1